Grid Transformer OLTC Full Servicing Project duration: 2 weeks Year: Feb 2016 Role: Main Contractor Project involved: Interfacing with ESB Networks on client’s behalf for isolation […]
Ring Main Unit Upgrade Works Project duration: 3 months Year: Feb 2014 Role: Main Contractor Project involved: Disconnection and removal of RMU Supply, installation and commissioning […]
1) Medium Voltage Switchgear Upgrade Works Project duration: 4 months Year: 2013 Role: Main Contractor Project involved: Lead design consultants on MV switchgear required to replace […]
1) Radio Centre Upgrade Project Project duration: 4 months Year: 2008 Role: Main Contractor Project involved: Manufacture, supply, installation, integration and commissioning of a new containerised […]
Customer Upgrade from LV to MV supply Project duration: 5 months Year: May 2015 Role: Specialist MV Sub-contractor Project involved: Design and specification of MV system […]
1) Upgrade Works to 3 Nr MV substations in Dublin hospital Project duration: 4 months each Year: 2010 & 2012 Role: Principal contractor and PSCS Project […]
New Site MV Switchgear and Transformer Installation & Commissioning Project duration: 2 months Year: June 2014 Role: Specialist MV Sub-contractor Project involved: Assembly and commissioning of […]
Client: Airport Authority Project duration: 4 months Role: Specialist Sub-Contractor Year: 2010 This project involved upgrading the MV switchgear and protection systems in a fully operational […]
Client: Airport Authority Project duration: 4 months Role: Specialist Sub-Contractor Year: 2010 This project involved upgrading the MV switchgear and protection systems in a fully operational […]
Client: Airport Authority Project duration: 6 months Role: Specialist Sub-Contractor Year 2009 This project involved: Replacing with modern equipment antiquated, oil-filled switchgear and transformers approaching end […]