This project involved upgrading the MV switchgear and protection systems in a fully operational airport environment.
Each cubicle was individually isolated and stripped of CTs, VTs and protection relays.
New CTs, VTs, protection relays and wiring looms were installed in each cubicle to facilitate integration into a fully automated Power Management System (PMS).
Each cubicle was recommissioned and returned to service.
Client: Airport Authority Project duration: 4 months Role: Specialist Sub-Contractor Year: 2010 This project involved upgrading the MV switchgear and protection systems in a fully operational […]
Client: Electrical Contracting Utility Project duration: 24 months Role: Project Management / Specialist Sub-Contractor We have acted as Project Managers and specialist Sub-Contractors on various large […]